How will Hyperscale Data fund the remaining work on its Michigan AI data center? In a regulatory filing reported on November 19, 2026, the Bitcoin mining company said the project would require another $74.8 million from November 2026 through March 2027. It warned that its cash and available financing were insufficient to cover planned spending and obligations over the following 12 months, raising substantial doubt about its ability to continue operating.
Hyperscale Data estimated the project’s construction and equipment costs at $122.1 million, of which $47.3 million had been paid by October 2026. At the end of September, it reported $17 million in unrestricted cash and $231 million in current liabilities. It had also sold approximately 1,113 BTC since late July, receiving about $74 million.
The company said its agreement with an AI customer could be worth up to $1.2 billion, but that potential value depends on the customer renewing twice and on Hyperscale Data fulfilling its obligations. It is not secured revenue available to cover the project’s near-term funding requirement.